A data processing center operates in a jurisdiction where newly introduced regulations have substantially increased penalties for data breaches. Which risk-register element is MOST important to update to reflect this change?

  • A Risk impact
  • B Risk trend
  • C Risk appetite
  • D Risk likelihood
Explanation

Increased breach penalties raise the potential financial and regulatory consequences of a data breach. The risk register should therefore update the risk impact assessment.