QuestionQ1136
Risk Response and ReportingWendy has identified a risk event in her project with a $75,000 impact and a 60 percent likelihood of occurring. Through research, her project team learns that the risk impact can be reduced to only $15,000 with a ten percent chance of occurrence. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this?
- A Mitigation
- B Avoidance
- C Transference
- D Enhancing