QuestionQ107

Risk Assessment

You are an experienced Project Manager entrusted with a project to develop a machine that produces auto components. You have scheduled meetings with the project team and key stakeholders to identify project risks. Which of the following is a key output of this process?

  • A Risk Register
  • B Risk Management Plan
  • C Risk Breakdown Structure
  • D Risk Categories
Explanation

Identifying project risks produces a risk register, which records identified risks and their relevant details for later analysis and response planning.