QuestionQ103

Risk Response and Reporting

You are the project manager for the GFT project. Your project involves using an electrical motor. Its specification states that if its temperature rises to 500 degrees Fahrenheit, the machine will overheat and must be shut down for 48 hours. If the machine overheats even once, it will delay the project's arrival date. To prevent this, while creating the response, you decided that if the machine's temperature reaches 450 degrees, it will be paused for at least an hour to normalize its temperature. This temperature of 450 degrees is referred to as?

  • A Risk identification
  • B Risk trigger
  • C Risk event
  • D Risk response
Explanation

A risk trigger is a predefined warning sign or threshold that indicates a risk is imminent and prompts a planned response. Reaching 450°F triggers the preventive pause before the motor reaches the 500°F overheating condition.