QuestionQ1020

Risk Response and Reporting

Which process addresses risks according to their priorities, updates the project management plan as needed, and incorporates resources and activities into the budget?

  • A Monitor and Control Risk
  • B Plan risk response
  • C Identify Risks
  • D Qualitative Risk Analysis
Explanation

Plan Risk Responses develops response actions for prioritized risks and integrates those actions into the project management plan, including the schedule and budget resources and activities.