QuestionQ21

VerifiedDesigning a Tailored Governance System

Which of the following is the FINAL action before the design of an IT governance system is completed?

Explanation

In the COBIT 2019 governance-system design workflow, a sourcing model is an input design factor and priority conflicts are addressed during the design analysis. Selecting the implementation method is the final listed action because it establishes how the tailored governance system will be put into practice.