QuestionQ56

VerifiedRisk Optimization

Which of the following is the BEST outcome metric for determining the effectiveness of IT risk-management processes?

Explanation

The number of events that affect business processes because responses to risks were delayed is a direct business-impact outcome. It indicates whether risk management is preventing or limiting realized risk; response time, satisfaction with training, and register-update frequency primarily measure process activity or perception. ISACA describes risk management as managing risk within the enterprise’s risk appetite and emphasizes assessing risks by their likelihood and business impact.