QuestionQ54

VerifiedSmart PV

If the SQA determines that the safety and quality requirements have not been met, the SQA shall communicate with the business personnel for confirmation. The business personnel’s opinions shall prevail.

Explanation

Safety quality assurance decisions must be based on compliance with the applicable safety and quality requirements and made with appropriate independence. Business personnel may be consulted, but their opinions cannot override a finding that those requirements are unmet. ISO 26262 functional-safety management includes project-independent organizational requirements.