QuestionQ48

VerifiedIntroduction to Huawei Data Center Facility and Critical Power Solutions

How long is the delivery time, not counting transportation, for the PowerPOD 3.0 system?

Explanation

PowerPOD 3.0 uses factory-completed prefabrication and commissioning, so the equipment arrives largely pre-assembled and pre-tested. This eliminates most of the onsite wiring work (traditional solutions need around 35 copper bars and 180 cables connected onsite), reducing the onsite construction/delivery time to only 2 weeks, versus roughly 2 months for a conventional power supply system.