QuestionQ63Verified/Cloud MigrationCopy linkReport a problemAsk AstroTutorSave questionWhich of the following is not included in the preliminary preparations for the cutover plan?AOn-site defenseBCutover targetCIntroduction to the current networkDRisk assessmentShow AnswerAnswerExplanationPreliminary cutover planning includes documenting the existing network, defining the cutover target, and assessing risk. On-site defense is an implementation-support activity rather than a preparatory planning item.Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!