QuestionQ66

VerifiedPrepare and present the solution

You have successfully installed, configured, and migrated the customer to the new Aruba CX data-center equipment.

Which documents are normally included in the post-installation deliverables?

Explanation

An equipment inventory documents the devices deployed for the customer and is a standard post-installation deliverable. Product data sheets and RFP responses are presales materials, while support-entitlement QR codes are not project documentation deliverables.