QuestionQ62

VerifiedArchitect the solution

Waratah Hospital, located in Australia, plans to relocate many data-center services to a new facility. (The remaining legacy data center is out of scope for this project.) Waratah Hospital has engaged an external consultant to help design the new data-center network.

Based on the data-center network-infrastructure requirements, the external consultant has produced a high-level design. The design document is summarized below.

Requirements and information:

  • Six racks in the data-center room (a single row).
  • Redundant top-of-rack leaf switches with back-to-front cooling in every rack, providing 10/25 Gbps connectivity to servers, storage, and other devices.
  • Four 100 GbE uplinks for each leaf switch.
  • The customer requested that all switch ports face the back of the rack racks (hot aisle).
  • OOB management for servers, storage, and networking must be supplied through an external switch with back-to-front cooling. This switch must be part of the solution. One OOB switch provides connectivity for two racks.
  • Core equipment for the OOBM network is being reused.
  • Middle-of-row spine switches.
  • The data center must connect to the hospital building using links that provide 400 Gbps.
  • Internet access is supplied through an existing firewall cluster with two firewalls, with one firewall in each data room. The second firewall runs in standby mode, and VRRP is used on the firewalls for failover. The data-center network must connect to these firewalls with links totaling 100 Gbps.
  • The external link is a dark-fiber direct link using single-mode fiber (OS2). The distance to the main hospital is 1.5 KM. The links will terminate on two core switches in the hospital.

The customer also requires:

  • 99.999% uptime for this life-critical environment.
  • Planned and unplanned downtime must be minimized.
  • Software upgrades are permitted only once per year with close to zero downtime.
  • All life-critical resources are accessed locally, and every resource exists within the hospital campus.
  • Waratah Hospital requires a highly secure environment for the data center. Encrypted wire-speed connectivity between the data room and the hospital is mandatory because the link between the buildings crosses a public road.
  • Waratah Hospital has a mix of virtualized (vSphere) servers, Nutanix storage, bare-metal servers, backup servers, and other devices.

Previously, the hospital experienced a security breach that caused data loss, network downtime, and identity theft.

Waratah Hospital requires a high-availability Aruba Fabric Composer deployment. How many nodes does the high-availability option support?

Explanation

Aruba Fabric Composer high availability is deployed as a three-node cluster, providing fault tolerance for Fabric Composer services while maintaining quorum.