QuestionQ41

Troubleshooting

Refer to the exhibit.

Question Image

Based on the screenshot, what is needed to correct the state shown in the exhibit?

  • A Use the same OS-CX image on the secondary that is active on primary.
  • B Use copy running-config vsx-peer on the secondary switch.
  • C Use the Enhanced Software Update process to correct the state.
  • D Use the force vsx-sync to start sync process.
Explanation

VSX configuration synchronization requires both switches to use identical software image versions. A software-version mismatch makes config synchronization non-operational, so the secondary must be loaded with the same active AOS-CX image as the primary.