You are installing a VSP 5000 system. It is connected to the power distribution, and you now want to power it on. Which three steps should you perform as part of the Power On sequence?

Choose three
Explanation

The power-on procedure energizes the system at the PDU breakers, enables the power supply with the PS ON/PS OFF switch on HSNPANEL0, and starts each CBX using its Power Button. A LAN reset is not a normal power-on operation, and Power LED status is a confirmation of the resulting state rather than a required power-on action.