Your organization requires a large amount of additional computing power within the next two weeks.

After those two weeks, the requirement for the extra resources will end.

Which approach is the most cost-effective?

Explanation

Compute Engine committed use discounts require a one- or three-year commitment and incur commitment charges for the entire term, including periods when the resources are not used. For a two-week, temporary capacity need, an on-demand virtual machine avoids long-term commitment and physical-hardware acquisition costs while allowing the resources to be stopped when the need ends.