QuestionQ43

VerifiedManaging Projects

You are the project manager for a Web development project. You want to obtain information about your competitors by hacking into their computers. You and the project team determine that, if the hacking attack is not performed anonymously, you will be traced. Therefore, you hire a professional hacker to work on the project.

This is an example of which type of risk response?

Explanation

Risk transference shifts ownership or exposure for a risk to a third party. Hiring a professional hacker transfers the execution and associated traceability risk from the project team to that external party.