QuestionQ42

VerifiedManaging Projects

Tomas is the project manager for the QWS Project and is concerned that project stakeholders will frequently want to change the project scope. His concern is based on the numerous open project issues and on how resolving those issues could result in additional project changes.

On which document are Tomas and the stakeholders working in this scenario?

Explanation

An issue log records current project issues, their owners, status, and resolution. Stakeholders use it to track and resolve open issues; a resolution may subsequently require a formal project change.