The active LTM device in a high-availability (HA) pair fails over at the same time that the network team reports a network-switch outage.

Which two items could have triggered the failover event?

Choose two
Explanation

A VLAN fail-safe can trigger failover when traffic on its configured VLAN is lost beyond the fail-safe timeout. An HA group can trigger traffic-group failover when monitored pool resources fall below their configured availability threshold. A standby reboot, the standby unit’s lost failover-VLAN connectivity, and GUI-only Auditor permissions do not independently make the active unit fail over.