QuestionQ48

Process Handling

What is the term for the risk that remains after a control is implemented?

  • A Residual risk
  • B Unaccepted risk
  • C Low risk
  • D Critical risk
Explanation

Residual risk is the risk remaining after controls have been implemented to reduce the initial level of risk.