QuestionQ3

PowerScale Hardware Installation

An engineer plans to install nodes in a cabinet that has room for additional hardware. All six PDU ports are occupied.

What is the recommended way to support the new nodes in this cabinet?

Explanation

New nodes require available power outlets on redundant power paths. Installing two additional PDUs adds the required outlet capacity while preserving the paired, independent PDU design used for redundant power; a single added PDU would not maintain that redundancy.