QuestionQ15

VerifiedPre-Deployment Check

An implementation engineer is on-site at a customer location, powering up a Dell PowerProtect Data Domain DD9910 system that has three DS600 expansion shelves attached.

What must be done before powering up the controller?

Explanation

In a Dell PowerProtect Data Domain deployment with DS60/DS600 expansion shelves, the correct power-up sequence is to power on the expansion shelves first and allow them to fully initialize before powering on the controller. This ensures the controller can properly detect and enumerate the attached storage shelves during its boot process. Therefore, the power cables must be connected to the expansion shelves and the shelves powered up prior to powering on the DD9910 controller.

Community Discussion

No comments yet. Be the first to start the discussion!