QuestionQ97
Project Life Cycle PhasesA project manager examines spending across the different phases of a project schedule. The schedule is divided into these project phases:
- Initiation: January to February
- Planning: March to May
- Execution: June to October
- Close: November to December
The following chart shows monthly expenses:

Given the monthly budget graph:

Which of the following project phases had the greatest cost?
- A Planning
- B Execution
- C Initiation
- D Close