QuestionQ89

Tools and Documentation

During project initiation, a project manager must create a project schedule and illustrate the project dependencies. Which of the following should the project manager use for this task?

  • A Waterfall method
  • B Simulation method
  • C Precedence diagramming method
  • D Cost ratio analysis
Explanation

The precedence diagramming method represents project activities as nodes connected by logical relationships, making it suitable for building a schedule and showing activity dependencies.