QuestionQ68

Project Life Cycle Phases

A project manager is unsure about obligations during the initiation phase, causing a delay in project documentation because approval owners are unclear. Which of the following documents should be completed next?

  • A Project charter
  • B RACI
  • C WBS
  • D SOW
Explanation

A RACI matrix assigns responsibility and accountability for project activities and decisions, including identifying the owner accountable for approvals. This resolves unclear approval ownership and supports timely completion of project documentation.