QuestionQ63

VerifiedProject Management Concepts

A stakeholder expresses concern to a project manager about the number of emails received before a coding release. Which of the following actions should the project manager take NEXT?

Explanation

The communications plan defines how project information is distributed, including appropriate methods and frequency for stakeholders. When a stakeholder identifies that communications are excessive, the plan should be revised to align communications with that stakeholder’s needs and expectations.