QuestionQ600

Project Management Concepts

A project manager purchases an extended warranty for a group of servers. Which risk management strategy is the manager using?

  • A Transfer
  • B Avoid
  • C Accept
  • D Mitigate
Explanation

Risk transfer shifts financial responsibility for specified losses to a third party. An extended warranty transfers covered repair or replacement costs for server failures to the warranty provider.