QuestionQ588

Tools and Documentation

A project is failing to progress as planned after the project manager’s departure. Which of the following is the best tool for documenting this information?

  • A Issue log
  • B Risk register
  • C Change log
  • D Defect log
Explanation

An issue log documents current problems that affect project performance, including their impact, owner, status, and resolution actions. The project manager’s departure is an existing event that is already disrupting progress.