QuestionQ575

Project Management Concepts

A new project manager is assigned to a project during its execution phase. The project manager identifies many potential areas that could prevent the project from completing its deliverables. What should the project manager do first?

  • A Review the project risk register.
  • B Update the defect tracker.
  • C Meet with stakeholders to discuss concerns.
  • D Add the potential blockers to the issues list.
Explanation

Potential threats to successful delivery are managed as project risks. Reviewing the project risk register first establishes the current documented risks, their analysis, assigned owners, and response plans; defects and issue lists apply to identified problems rather than potential blockers.