A project team reviews the project plan and related documents and identifies tasks that could be divided into smaller deliverables. Which of the following documents should the team revise first?

  • A Risk assessment
  • B Preliminary scope statement
  • C Work breakdown structure
  • D Milestone chart
Explanation

A work breakdown structure decomposes the project scope into smaller, manageable deliverables and work packages. It is the primary document to update when identified work needs further breakdown.