QuestionQ565

Tools and Documentation

Because of budget and schedule constraints, a PM arranged a meeting with all stakeholders during the planning phase to review the requirements and agree on an acceptable minimum viable product. Which of the following would document this input?

  • A Project change management plan
  • B Project management plan
  • C Project transition plan
  • D Project communication plan
Explanation

Stakeholder-agreed requirements and the acceptable minimum viable product define the project scope and are documented in the project management plan, including its scope-related baselines and subsidiary plans.