QuestionQ556

Project Management Concepts

A project owner informs a project manager that a 15% bonus will be paid if the project is completed three weeks ahead of its original plan without adding cost. Which option best describes what the project manager should do?

  • A Fast-track the project schedule.
  • B Crash the project schedule.
  • C Monitor the project performance.
  • D Level the project resources.
Explanation

Fast-tracking compresses the schedule by performing activities in parallel that were originally planned sequentially, allowing earlier completion without necessarily increasing cost. Crashing generally requires additional resources and therefore additional cost.