QuestionQ554
Project Management ConceptsDuring a status meeting, the development team reviews the work and identifies an unforeseen dependency on a critical project activity. Consequently, the project will most likely be delayed. Which action should the project manager MOST likely take?
- A Work with the project scheduler to update the project timeline.
- B Communicate to the stakeholders about the updated timeline.
- C Ask the development team to fast-track upcoming activities.
- D Add two resources so the critical activities will finish on time.