QuestionQ530

Project Management Concepts

A project coordinator has initiated a new project and is reviewing these customer-provided characteristics:

  • Two developers
  • High uncertainty regarding existing systems
  • Risk of frequent requirements changes
  • Tight deadlines

Which project methodology would be BEST to use in this situation?

  • A PRINCE2
  • B Scrum
  • C SAFe
  • D XP
Explanation

Extreme Programming (XP) is suited to a small development team working with changing requirements and fixed-time delivery risk. Its short feedback cycles, frequent releases, automated testing, refactoring, and close collaboration help the team discover and safely adapt to uncertainty in existing systems while meeting tight deadlines.