QuestionQ53

VerifiedProject Management Concepts

During an executive call, a project sponsor learned about issues with the project but could not provide details about the next steps. Which of the following needs to be revised?

Explanation

A communication plan defines what project information stakeholders receive, when they receive it, and how issues and required actions are communicated. It should ensure that the project sponsor is informed of issues and their planned next steps before or during executive-level discussions.