Which of the following key project components organizes deliverables into manageable pieces, ensuring the appropriate steps are performed and the project's core objectives are achieved?

  • A WBS
  • B RACI
  • C RFP
  • D PERT
Explanation

A work breakdown structure (WBS) hierarchically divides the project’s deliverables and scope into manageable work components, enabling the work needed to meet project objectives to be planned and carried out.