QuestionQ511

Project Management Concepts

A project manager who completed a project some time ago continues to receive questions from another project manager currently managing a similar project. Which of the following is the MOST likely cause of this situation?

  • A The retrospective session feedback was not communicated properly.
  • B The project resources were released ahead of time.
  • C The documentation was not archived as per the PMO standards.
  • D The validation of deliverables is running behind schedule.
Explanation

Project documentation should be archived according to PMO standards so that project records, knowledge, and lessons learned are available for future similar work. If it is not archived properly, subsequent project managers must rely on the former project manager for information.