QuestionQ502
Project Management ConceptsA project manager identifies that a resource is overloaded and is not completing tasks on time. After reviewing the Gantt chart, the project manager sees that the resource has multiple simultaneous tasks that can be performed independently. What should the project manager do next?
- A Change the precedence of the tasks to “finish-to-start”.
- B Evaluate and modify the schedule with a burndown chart.
- C Assign additional resources to prevent overwork.
- D Perform critical path analysis.