Project Management ConceptsFollowing a successful performance test of a customized web application, the end user refuses to accept the solution because it does not meet the company’s needs. What should the project manager do first to manage the conflict?
- A Ignore the end user if the management team is satisfied with the solution.
- B Ask the user to submit a request to align the solution to the business's needs.
- C Force the user to use the solution, as the system was custom built.
- D Review project requirements and validate compliance with the user.