QuestionQ486

Tools and Documentation

A project manager is working with a new team to review a requirement for a new project. The project manager wants to produce artifacts that include roles and responsibilities. Which artifact type best fits these requirements?

  • A RACI chart
  • B Gantt chart
  • C Burndown chart
  • D Organizational chart
Explanation

A RACI chart assigns and communicates roles and responsibilities for project activities or decisions: Responsible, Accountable, Consulted, and Informed.