QuestionQ48

VerifiedTools and Documentation

A project team takes part in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

Explanation

A project quality assurance plan defines how established processes and procedures will be evaluated and monitored so that developed products are produced in conformance with quality requirements. Quality assurance is process-focused, whereas quality control monitors specific product results.