Following an approved change request, the project manager updates the project plan to reflect the added feature and the revised production release date. Which change control process should the project manager perform NEXT?

  • A Validate the change implementation.
  • B Implement the change.
  • C Conduct an impact assessment.
  • D Communicate the change deployment.
Explanation

Once an approved change has been incorporated into the project management plan, the authorized change should be implemented. Impact analysis precedes approval, and validation follows implementation.