QuestionQ45

VerifiedProject Management Concepts

A project manager is creating a project management plan. The resource assignments have been completed. Which of the following steps should have been finished before the resource assignments were completed?

Explanation

Resources must be assigned to defined units of work, such as activities or work packages. Defining the work establishes what effort and capabilities are required, making resource assignments possible.

Community Discussion

No comments yet. Be the first to start the discussion!