Which of the following are regarded as core elements of a project closeout report?

Choose two
  • A Gap analysis of critical path
  • B Project scope, schedule, and cost
  • C Company vision, mission, and goals
  • D Results and outcomes of the project
Explanation

A project closeout report assesses performance against the project’s scope, schedule, and cost, and records the project’s results and outcomes. These details establish what was planned, what was delivered, and how the project performed.