QuestionQ436

Tools and Documentation

A project team member prepared a user guide during the last ten days. Based on the following scatter diagram:

Question Image

Which of the following may be formally concluded?

  • A The team member prioritized other tasks over the completion of this task.
  • B The team member had performance issues over time.
  • C There is a negative correlation with time and output.
  • D This is a display of units of outstanding work to predict completion.
Explanation

The data show that output decreases as time increases, as indicated by the downward-sloping trendline. A scatter plot establishes correlation, not the cause of that relationship, so it cannot substantiate claims about prioritization or performance problems.