QuestionQ417

Project Life Cycle Phases

At the end of the execution phase, a project manager was concerned that the results were not meeting expectations. After reviewing the SOW, the project manager determined that the vendor had delivered everything included in the contract. Which action should the project manager complete next?

  • A Perform a gap analysis.
  • B Escalate the issue.
  • C Submit a change request.
  • D Approve deliverables.
Explanation

A gap analysis identifies the difference between the expected results and the contracted deliverables that were provided. It clarifies whether the shortfall stems from omitted requirements, unclear expectations, or another issue before escalation or a change request is considered.