QuestionQ404

Project Management Concepts

During a project touchpoint, several stakeholders report confusion about who is responsible for attending weekly calls. Another stakeholder says they are receiving too many email notifications. Which of the following should the project manager review?

  • A WBS
  • B RACI
  • C SOW
  • D SLA
Explanation

A RACI matrix clarifies stakeholder responsibility and involvement by identifying who is Responsible, Accountable, Consulted, and Informed for each activity. It can establish who should attend weekly calls and who should receive relevant communications.