QuestionQ402

Project Life Cycle Phases

A project manager and an IT manager are developing operational training and handoff procedures while also considering a move-to-production date. Which of the following are they working on?

  • A Risk plan
  • B Transition plan
  • C Communications plan
  • D QA plan
Explanation

A transition plan defines how a solution is handed from the project team to operations, including operational training, handoff procedures, and the schedule for moving the solution into production.