A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

  • A Data plan
  • B Contingency plan
  • C Rollback plan
  • D Recovery plan
Explanation

A contingency plan is developed to address identified risks before they occur by outlining alternative actions and response strategies. Since the project is scheduled during peak hurricane season, developing a contingency plan allows the team to prepare mitigation and recovery procedures should a hurricane impact the work. Recovery plans (D) are executed after a disaster occurs, while a data plan (A) is unrelated, and a rollback plan (C) applies to system deployments rather than environmental risks.