A project team identifies a bug during user acceptance testing. Which of the following is the BEST way to communicate that bug to the development team?

  • A Call the development lead to discuss the fixes for the bug.
  • B Include the bug issue as part of the status update for stakeholders.
  • C Issue a change request.
  • D Add the bug issue to the project's risk register.
Explanation

A bug found during user acceptance testing requires corrective work that should be formally documented, assessed, approved as appropriate, and tracked through change control. A change request provides that mechanism.