A project manager has been notified that delivery of the required IT equipment will be delayed. What should the project manager do FIRST?

  • A Make an impact assessment.
  • B Prepare a new purchase order.
  • C Select a new vendor.
  • D Create a risk register.
Explanation

A delivery delay is a current project issue that can affect the schedule, cost, resources, and dependent activities. Its impact must be assessed before committing to actions such as issuing a new purchase order or changing vendors, so that any response is appropriately controlled and justified.